The ST. Sebastian North Lock Gate and Pumping Station Project has start over two and half years, the total progress is more than 90%. The project including two parts, one is the civil work for pumping station and lock gate, the other one is to supply and install the mechanical and electrical operation system. Till now, the pumping station civil work is complete, the lock gate is complete 65%. ALL the machines and equipment importation work has completed, the installation of pumping station complete 70%, lock gate 50%. The testing work for mechanical and electrical equipment has started, during next 3 month it will be finished with all the major civil work together.